Bridging the Interconnection Gap
This tutorial demonstrates how to use EASI to design a bridging power microgrid for the Cypress Ridge development in Texas.The developer targets about 1 MW of grid capacity, but interconnection is expected to take 3 to 5 years, so EASI models a four-year bridge period with grid availability starting January 1 and a $100,000 cost of delay. The load profile is uploaded, the project keeps defaults while requiring at least 50% renewable fraction, and it uses the Entergy GS utility rate shown in the demo. Results show performance across the bridge and grid-connected phases, hardware-focused costs, projected payback in about 4.1 years, and related financial metrics and assumptions.
Chapters Timeline
- 0:00Bridge power challenge overview
- 0:58EASI interface and workflow
- 1:48Energy goal and bridge parameters
- 4:06Optimized system results
- 5:23Update assumptions and view products